Issue - decisions

York Central Access Road and Station Access Improvements

05/03/2021 - York Central Access Road and Station Access Improvements

(i)              In respect of York Central Access the Investment Committee approved that:

(a)         The conditions on the York Central Access & York Station Frontage full business case approval of 13 March 2019 are discharged.

(b)        Further development costs of £2.252 million are approved (to be funded from the West Yorkshire plus Transport Fund) taking the total development costs approved to £5.532 million

(c)         The Combined Authority enters into an addendum to the existing funding agreement with City of York Council for additional development costs of £2.252 million (to be funded from the West Yorkshire plus Transport Fund)

(d)        The Combined Authority’s West Yorkshire plus Transport Fund and Transforming Cities Fund allocations will be rationalised into three separate projects, York Central. York Station Gateway and Askham Bar Park & Ride Improvements.

(e)         Future approvals are made in accordance with the assurance pathway and approval routes outlined in this report. This will be subject to the projects remaining within the tolerances outlined in this report.