Brownfield Housing Fund: Points Cross, Hunslet Road

05/03/2021 - Brownfield Housing Fund: Points Cross, Hunslet Road

(i)              In respect of Points Cross, Hunslet Road the Investment Committee approved that:

(a)         The Points Cross Phase 1 scheme proceeds through decision point 5 (full business case with finalised costs) and work commences on activity 6 (delivery)

(b)        Approval to £2.755 million is given from the Brownfield Housing Fund.

(c)         The Combined Authority enters into a funding agreement with Guinness Developments Ltd which is part of the Guinness Partnership for the Points Cross scheme for expenditure up to £2.755 million from the Brownfield Housing Fund.

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.