Getting Building Fund: Leeds City Centre 'Grey to Green'

04/02/2021 - Getting Building Fund: Leeds City Centre 'Grey to Green'

(i)              That in respect of the Leeds City Centre Grey to Green the Investment Committee approved:

(a)        The Grey to Green scheme proceeds through decision point 4 (full business case) and work commences on activity 5 (full business case with finalised costs)

(b)        An indicative approval of £8.6 million is given from the Getting Building Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5.  The total scheme cost is forecast at £11.886 million.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.