Resolved: In respect of LCCP Infirmary Street -
That following a recommendation from the Investment Committee, the Combined Authority approves:
(a) That the Infirmary Street Gateway scheme proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).
(b) That an indicative approval to the total project value of £8.90 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(c) That future approvals are made in accordance with the Assurance pathway and Approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.