Resolved: That following a recommendation from the Investment Committee, the Combined Authority approves:
(a) That the Clifton Business Park (Enterprise Zone) scheme proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs).
(b) That development costs of £3.156 million are approved in order to assist in the progress the scheme to decision point 5 (full business case with finalised costs).
(c) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.