Temple Green Park and Ride Extension

10/10/2019 - Temple Green Park and Ride Extension

Resolved:  That following a recommendation from the Investment Committee the Combined Authority approves:

(a)       That the Leeds Public Transport Investment Programme Temple Green Park & Ride Extension project proceeds through outline business case (decision point 3) and work commences on full business case (decision point 4).

(b)       That an indicative approval to the Combined Authority’s contribution of £6.954 million (which will be funded through the Leeds Public Transport Investment Programme) is given, with full approval to spend being granted once the scheme has progressed through the assurance process to full business case plus finalised costs (decision point 5). The total project value is £7.386 million.

(c)        That development costs of £841,000 are approved in order to progress the scheme to full business case plus finalised costs (decision point 5), with a further £1.42 million approved to fund land purchase costs expended at risk by Leeds City Council, taking total approval to £2.261 million.

(d)       That the Combined Authority enters into a variation of the existing Funding Agreement with Leeds City Council for Leeds Public Transport Investment Programme schemes, for expenditure of up to £2.261million from the Leeds Public Transport Investment Programme fund.

(e)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision points 4 and 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.