To approve the change request to the A629
phase 1a scheme authorizing additional £343,344 delivery
costs, and the re-allocation of £39,812 from the post
construction evaluation budget into the A629 (programme) monitoring
budget. This takes the total outturn cost for the scheme to
£8,639,999.
To approve that the Combined Authority enters into an addendum to
the existing funding agreement with Calderdale Metropolitan Borough
Council for additional expenditure of up to £343,344 from the
West Yorkshire Plus Transport Fund.