Agenda item

Capital Spending and Project Approvals

Decision:

(i)          That in respect of West Yorkshire Mass Transit programme the Investment Committee recommended to the Combined Authority that:

(a)        The West Yorkshire Mass Transit programme proceeds through decision point 1 (Strategic assessment) and work commences on activity 2 (Strategic outline case) 

(b)        An approval for development funding is agreed for £2.041 million from WY+TF Transformational Fund to develop the feasibility of the scheme.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report. 

(ii)         That in respect of the A64 Bus Priority and Park and Ride the Investment Committee recommended to the Combined Authority that:

(a)        The A64 Bus Priority & Park & Ride package proceeds through decision point 2 (Strategic outline case) and work commences on activity 3 (Outline business case).

(b)        An indicative approval of £7 million is given from the Transforming Cities Fund with full approval to spend being granted once the scheme package has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the package remaining within the tolerances outlined in this report.

(iii)           That in respect of the Integrated Corporate System project the Investment Committee recommended to the Combined Authority that:

(a)        The Integrated Corporate Systems project proceeds through decision point 2 (Strategic outline case) and work commences on activity 4 (full business case).

(b)        An indicative approval to the total project value of £1.5 million is given from the Combined Authority’s own capital programme and reserves. with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 4.

(c)        Development costs of £150,000 are approved in order to progress the scheme to decision point 4 (Full business case).

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 4 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(iv)           That in respect of the Bradford Strategic Transport Model the Investment Committee recommended to the Combined Authority that:

(a)        The Bradford Strategic Transport Model project proceeds through Decision Point 2 (Strategic outline case) and work commences on Activity 5 (full business case with finalised costs).

(b)        An indicative approval to the Combined Authority’s contribution of £367,000 (which will be funded through the West Yorkshire Transport Fund) is given. The remainder of the funding is from City of Bradford Metropolitan District Council (£342,000). The total project value is £709,000.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(v)            That in respect of the Leeds City Centre Cycle Connectivity the Investment Committee recommended to the Combined Authority that:

(a)        The TCF: Leeds City Centre Cycle Connectivity project proceeds through decision point 3 (Outline business case) and work commences on activity 5 (Full business case with finalised costs).

(b)        An indicative approval to the total project value of £7.81 million is given from the TCF fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)        Additional development costs of £1.085 million are approved, in order to progress the scheme to decision point 5 (Full business case with finalised costs), taking the total project approval to £1.235 million.

(d)        The Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £1.235 million from the TCF fund.

(e)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(vi)           That in respect of the Rail Accessibility Programme – Horsforth and Crossgates the Investment Committee recommended that:

(a)        The Rail Accessibility Programme (RAP) passes through decision point 3 (Outline business case), in preparedness for work to commence on activity 4 (Full business case) when scheme funding has been secured.

(b)        Investment Committee are sighted on the total project value of £8.371 million. The funding source will be confirmed at decision point 4, when funding has been secured, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances, to be agreed and funding being secured.

(vii)         That in respect of the A629 Phase 1b the Investment Committee recommended that:

(a)        The A629 phase 1b project proceeds through decision point 4 and work commences on activity 5 (Full business case with finalised costs).

(b)        An indicative approval to the total project value of £27.83 million is given from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(viii)        That in respect of Leeds Bus Station Gateway the Investment Committee recommended that:

(a)        an indicative approval for an additional £224,000 from the ULEB programme, bringing the total project to £5.208 million, is given, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs)

(b)        The change request to the Leeds Bus Station Gateway - to increase the development costs from £750,000 to £1.204 million (additional funding of £454,000) is approved.

(c)        The change request to the Leeds Bus Station Gateway - to extend the delivery timeframe from March 2021 to March 2022 is approved.

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outline in this report.

(ix)           That in respect of the A660 Signals the Investment Committee  recommended that:

(a)        The A660 Signals Upgrade Scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

(b)        That full approval to the Combined Authority’s contribution of £733,000 is given from the Leeds Public Transport Investment Programme fund. The total project value is £1.056 million. 

(c)        The Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £733,000 from the Leeds Public Transport Investment Programme fund.

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(x)            That in respect of the West Yorkshire Cycling and Walking Infrastructure Plans the Investment Committee recommended that:

(a)        The West Yorkshire Local Cycling and Walking Infrastructure Plans scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

(b)        Full approval to the total project value of £600,000 is given from Local Transport Plan - Integrated Transport Block programme.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(xi)           That in respect of the Transport ICT (CoSA) scheme the Investment Committee recommended that:

(a)        The Transport ICT (CoSA) scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

(b)        Full approval to the Combined Authority’s contribution of £200,000 is given from the Local Transport Plan – Integrated Transport Block programme. The total project value is £200,000. 

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

Minutes:

(i)          That in respect of West Yorkshire Mass Transit programme the Investment Committee recommended to the Combined Authority that:

(a)        The West Yorkshire Mass Transit programme proceeds through decision point 1 (Strategic assessment) and work commences on activity 2 (Strategic outline case) 

(b)        An approval for development funding is agreed for £2.041 million from WY+TF Transformational Fund to develop the feasibility of the scheme.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report. 

(ii)         That in respect of the A64 Bus Priority and Park and Ride the Investment Committee recommended to the Combined Authority that:

(a)        The A64 Bus Priority & Park & Ride package proceeds through decision point 2 (Strategic outline case) and work commences on activity 3 (Outline business case).

(b)        An indicative approval of £7 million is given from the Transforming Cities Fund with full approval to spend being granted once the scheme package has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the package remaining within the tolerances outlined in this report.

(iii)           That in respect of the Integrated Corporate System project the Investment Committee recommended to the Combined Authority that:

(a)        The Integrated Corporate Systems project proceeds through decision point 2 (Strategic outline case) and work commences on activity 4 (full business case).

(b)        An indicative approval to the total project value of £1.5 million is given from the Combined Authority’s own capital programme and reserves. with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 4.

(c)        Development costs of £150,000 are approved in order to progress the scheme to decision point 4 (Full business case).

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 4 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(iv)           That in respect of the Bradford Strategic Transport Model the Investment Committee recommended to the Combined Authority that:

(a)        The Bradford Strategic Transport Model project proceeds through Decision Point 2 (Strategic outline case) and work commences on Activity 5 (full business case with finalised costs).

(b)        An indicative approval to the Combined Authority’s contribution of £367,000 (which will be funded through the West Yorkshire Transport Fund) is given. The remainder of the funding is from City of Bradford Metropolitan District Council (£342,000). The total project value is £709,000.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(v)            That in respect of the Leeds City Centre Cycle Connectivity the Investment Committee recommended to the Combined Authority that:

(a)        The TCF: Leeds City Centre Cycle Connectivity project proceeds through decision point 3 (Outline business case) and work commences on activity 5 (Full business case with finalised costs).

(b)        An indicative approval to the total project value of £7.81 million is given from the TCF fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)        Additional development costs of £1.085 million are approved, in order to progress the scheme to decision point 5 (Full business case with finalised costs), taking the total project approval to £1.235 million.

(d)        The Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £1.235 million from the TCF fund.

(e)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(vi)           That in respect of the Rail Accessibility Programme – Horsforth and Crossgates the Investment Committee recommended that:

(a)        The Rail Accessibility Programme (RAP) passes through decision point 3 (Outline business case), in preparedness for work to commence on activity 4 (Full business case) when scheme funding has been secured.

(b)        Investment Committee are sighted on the total project value of £8.371 million. The funding source will be confirmed at decision point 4, when funding has been secured, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances, to be agreed and funding being secured.

(vii)         That in respect of the A629 Phase 1b the Investment Committee recommended that:

(a)        The A629 phase 1b project proceeds through decision point 4 and work commences on activity 5 (Full business case with finalised costs).

(b)        An indicative approval to the total project value of £27.83 million is given from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(viii)        That in respect of Leeds Bus Station Gateway the Investment Committee recommended that:

(a)        an indicative approval for an additional £224,000 from the ULEB programme, bringing the total project to £5.208 million, is given, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs)

(b)        The change request to the Leeds Bus Station Gateway - to increase the development costs from £750,000 to £1.204 million (additional funding of £454,000) is approved.

(c)        The change request to the Leeds Bus Station Gateway - to extend the delivery timeframe from March 2021 to March 2022 is approved.

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outline in this report.

(ix)           That in respect of the A660 Signals the Investment Committee  recommended that:

(a)        The A660 Signals Upgrade Scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

(b)        That full approval to the Combined Authority’s contribution of £733,000 is given from the Leeds Public Transport Investment Programme fund. The total project value is £1.056 million. 

(c)        The Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £733,000 from the Leeds Public Transport Investment Programme fund.

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(x)            That in respect of the West Yorkshire Cycling and Walking Infrastructure Plans the Investment Committee recommended that:

(a)        The West Yorkshire Local Cycling and Walking Infrastructure Plans scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

(b)        Full approval to the total project value of £600,000 is given from Local Transport Plan - Integrated Transport Block programme.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

(xi)           That in respect of the Transport ICT (CoSA) scheme the Investment Committee recommended that:

(a)        The Transport ICT (CoSA) scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

(b)        Full approval to the Combined Authority’s contribution of £200,000 is given from the Local Transport Plan – Integrated Transport Block programme. The total project value is £200,000. 

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

Supporting documents: