Agenda item

Capital Spending and Project Approvals

Decision:

Resolved:

 

(i)         In respect of Raising Aspirations, the Investment Committee recommends to the Combined Authority:

 

(a)       That the Raising Aspirations project proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs).

 

(b)       That an indicative approval is given to the total project value of £400,000 to be funded by the Combined Authority from the secured business rates pool funding with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(ii)        In respect of the A647 Bus Priority Corridor, the Investment Committee recommends to the Combined Authority:

 

(a)       That the Leeds Public Transport Investment Programme: A647 Corridor project proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case).

 

(b)       That an indicative approval to the total project value of £9.68 million is given from Leeds Public Transport Investment Programme funding with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 4 (full business case) and decision point 5 (full business case with finalised costs) through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(iii)       In respect of the Corridor Improvement Programme Phase 1 - Huddersfield Southern Corridors, the Investment Committee recommends to the Combined Authority:

 

(a)       That the Huddersfield Southern Corridors scheme proceeds through decision point 3 and work commences on activity 4 (full business case).

 

(b)       That an indicative approval to the total project value of £8.199 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That development costs of £2.234 million are approved in order to progress the scheme to decision point 5 (full business case with finalised costs) taking the total project approval to £2.534 million. This includes land acquisition costs of £1.6 million.

 

(d)       That the Combined Authority enters into an addendum to the existing funding agreement with Kirklees Council for expenditure of up to £2.534 million from the West Yorkshire plus Transport Fund.

 

(e)       That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(iv)       In respect of Halifax Town Centre - Northgate House, the Investment Committee approves:

 

(a)       That the Halifax Town Centre Northgate House scheme proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).

 

(b)       That an indicative approval of £3 million is given from the Local Growth Fund (Growth Deal 3) towards a total scheme cost of £10.655 million with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 (full business case with finalised costs) through a delegation to the combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(v)        In respect of Rochdale Canal, the Investment Committee recommends to the Combined Authority:

 

(a)       That the Rochdale Canal Towpath Phase 2 - Hebden Bridge to Todmorden scheme proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).

 

(b)       That an indicative approval to total project cost of £2.101 million of which £1.971 million will be Combined Authority funding which will be funded from the DfT Cycle Safety Grant and Cycle City Ambition Grant with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(vi)       That the WYTF (Transport Fund) A629 Halifax Road Phase 5 project funding approval by the Combined Authority on 10 May 2018 be amended to:

 

(i)         That development costs of £4.116 million are approved in order to progress the scheme to decision point 4 (full business case), taking the total project approval to £4.418 million and that an addendum to the funding agreement with Kirklees Council for the additional £4.116 million is entered into.

Minutes:

The Committee considered a report on proposals for the progression of, and funding for, a number of West Yorkshire Combined Authority supported projects, including West Yorkshire plus Transport Fund (Transport Fund) and Growth Fund at stages 1, 2 and 3 of the Combined Authority’s assurance process.

 

Members discussed the proposals for the progression of the following five schemes which were detailed in the submitted report:

 

·         Raising Aspirations

·         A647 Bus Priority Corridor

·         Corridor Improvement Programme Phase 1 – Huddersfield Southern Corridors

·         Halifax Town Centre – Northgate House

·         Rochdale Canal – Cycle Safety Fund

 

Copies of the business case summaries were attached at Appendices 2-6 of the submitted report.  It was requested that the summary in future reports should include an impact assessment column to provide information showing how the schemes will meet targets in respect of social and economic benefits.

 

Members asked for a discussion item on skills to be brought to a future meeting to ensure Members continue to make informed decision on skills related schemes.

 

The Committee was also provided with details of the following project decisions delegated to the Combined Authority’s Managing Director since the last meeting:

 

·         York Outer Ring Road Phase 2 (Monks Cross)

·         Urban Traffic Management Control (UTMC) scheme – Element A

·         Calderdale multi-modal studies

·         Glasshoughton Southern Link Road

·         Leeds City Region Employment Hub

 

Copies of the business case summaries were attached at Appendix 7 and details of the schemes outlined in the report.

 

In respect of Garnett’s Wharf, Otley – Growing Places Fund loan 104, it was noted that the Combined Authority’s Director of Delivery had approved the decision point 7 project closure report and details were outlined in the report.

 

It was reported that the WY+TF (Transport Fund) A629 Halifax Road Phase 5 project was approved by the Combined Authority on 10 May 2018 to proceed through decision point 3 and work commence on activity 4 (full business case).  However there was a £3,000 error in the figures reported and approval was now sought to amend the development costs figure from £4.113 million to £4.116 million.  It was agreed that an addendum to the funding agreement be entered into with Kirklees Council.

 

Resolved:

 

(i)         In respect of Raising Aspirations, the Investment Committee recommends to the Combined Authority:

 

(a)       That the Raising Aspirations project proceeds through decision point 2 and work commences on activity 5 (full business case with finalised costs).

 

(b)       That an indicative approval is given to the total project value of £400,000 to be funded by the Combined Authority from the secured business rates pool funding with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(ii)        In respect of the A647 Bus Priority Corridor, the Investment Committee recommends to the Combined Authority:

 

(a)       That the Leeds Public Transport Investment Programme: A647 Corridor project proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case).

 

(b)       That an indicative approval to the total project value of £9.68 million is given from Leeds Public Transport Investment Programme funding with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 4 (full business case) and decision point 5 (full business case with finalised costs) through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(iii)       In respect of the Corridor Improvement Programme Phase 1 - Huddersfield Southern Corridors, the Investment Committee recommends to the Combined Authority:

 

(a)       That the Huddersfield Southern Corridors scheme proceeds through decision point 3 and work commences on activity 4 (full business case).

 

(b)       That an indicative approval to the total project value of £8.199 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That development costs of £2.234 million are approved in order to progress the scheme to decision point 5 (full business case with finalised costs) taking the total project approval to £2.534 million. This includes land acquisition costs of £1.6 million.

 

(d)       That the Combined Authority enters into an addendum to the existing funding agreement with Kirklees Council for expenditure of up to £2.534 million from the West Yorkshire plus Transport Fund.

 

(e)       That future approvals are made in accordance with the approval pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(iv)       In respect of Halifax Town Centre - Northgate House, the Investment Committee approves:

 

(a)       That the Halifax Town Centre Northgate House scheme proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).

 

(b)       That an indicative approval of £3 million is given from the Local Growth Fund (Growth Deal 3) towards a total scheme cost of £10.655 million with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 (full business case with finalised costs) through a delegation to the combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(v)        In respect of Rochdale Canal, the Investment Committee recommends to the Combined Authority:

 

(a)       That the Rochdale Canal Towpath Phase 2 - Hebden Bridge to Todmorden scheme proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).

 

(b)       That an indicative approval to total project cost of £2.101 million of which £1.971 million will be Combined Authority funding which will be funded from the DfT Cycle Safety Grant and Cycle City Ambition Grant with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

 

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

 

(vi)       That the WYTF (Transport Fund) A629 Halifax Road Phase 5 project funding approval by the Combined Authority on 10 May 2018 be amended to:

 

(i)         That development costs of £4.116 million are approved in order to progress the scheme to decision point 4 (full business case), taking the total project approval to £4.418 million and that an addendum to the funding agreement with Kirklees Council for the additional £4.116 million is entered into.

 

Supporting documents: