Agenda item

Corridor Improvement Programme (Phase 1)

Decision:

Resolved:

(a)       In respect of Corridor Improvement Programme Phase 1 – A647 Dawsons Corner –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Dawson’s Corner project proceeds through decision point 3 and work commences on activity 4 (full business case).

(ii)        That an indicative approval is given to the total project value of £20.159 million, with the Combined Authority’s contribution of £19 million (which will be funded through £15 million from the CIP Phase 1 fund and £4 million from the LPTIP fund) is given with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total project value is £20.159 million.

(iii)       That  development costs of £1.599 million, (including £499,000 additional development costs and £1.1 million land assembly costs) are approved in order to progress the scheme to decision point 5 (full business case with finalised costs), taking the approval to £2.607 million

(iv)       That the Combined Authority issue an addendum to the existing funding agreement with Leeds Council for additional expenditure of up to £1.599 million from the West Yorkshire plus Transport Fund taking the total value to £2.607 million.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(b)       In respect of Corridor Improvement Programme Phase 1 – Dyneley Arms –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Dyneley Arms junction project proceeds through decision point 3 and work commences on activity 4 (full business case) and 5.

(ii)        That an indicative approval to the total project value of £2.747 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs)

(iii)       That additional development costs of £373,000 (which include £250,000 for land assembly) are approved in order to progress the scheme to decision point 5 (full business case with finalised costs) taking the total approval to £775,000.

(iv)       That the Combined Authority issues an addendum to the existing funding agreement with Leeds Council for additional expenditure of up to £373,000 from the West Yorkshire plus Transport Fund (giving a total funding agreement value of £775,000).

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(c)        In respect of Corridor Improvement Programme Phase 1 – Fink Hill scheme –

That following a recommendation from the Investment Committee, the   Combined Authority approves:

(i)         That the Corridor Improvement Programme Phase 1 Fink Hill project proceeds through decision point 3 (outline business case) and work commences on activity 4 (full business case).

(ii)        That an indicative approval to the total project value of £4.150 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That additional development costs of £404,000 are approved in order to progress the scheme to decision point 4 (full business case) taking the total project approval to £519,000.

(iv)       That the Combined Authority enter into an addendum to the existing funding agreement with Leeds City Council for additional expenditure of up to £404,000 from the West Yorkshire plus Transport Fund taking the total value to £519,000.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject remaining within the tolerances outlined in the report.

(d)       In respect of Corridor Improvement Programme Phase 1 – A650 Newton Bar scheme –

That the Combined Authority approves

(i)         That the Corridor Improvement Programme Phase 1 A650 Newton Bar project proceeds through decision point 3 and work commences on activity 4 (full business case).

(ii)        That an indicative approval to the total project value of £6.752 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That development costs of £129,800 are approved in order to progress the scheme to decision point 4 (full business case) taking the total project approval to £204,800.

(iv)       That the Combined Authority enters into an addendum to the existing funding agreement with Wakefield Council for additional expenditure of up to £129,800 from the West Yorkshire plus Transport Fund taking the total value to £204,800.

(v)        That future approvals are made in accordance with the §assurance pathway and approval route outlined in the submitted report (including through delegation to the Combined Authority’s Managing Director at decision points 4 and 5) following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.