Agenda and decisions

ARCHIVED - West Yorkshire and York Investment Committee - Tuesday, 8th June, 2021 11.00 am

Venue: City Exchange, 11 Albion St, Leeds LS1 5ES

Note: This meeting will be held at City Exchange, 11 Albion St, Leeds LS1 5ES. In line with the Government’s social distancing restrictions, there will be very limited capacity for observers of the meeting. If you would like to attend to observe the meeting in person, please email: governanceservices@westyorks-ca.gov.uk to request a place, clearly stating the name, date and start time of the committee and include your full name and contact details, no later than 24 hours before the meeting begins. Please note that the pre-booked places will be allocated on a ‘first come, first served’ basis and once pre-booked capacity has been reached there will be no further public admittance to the meeting. On receipt of your request, colleagues will provide a response to you. Please Note: For those who are attending the meeting, please bring a face covering, unless you are exempt. 

Items
No. Item

1.

Apologies for Absence

2.

Declarations of Disclosable Pecuniary Interests

3.

Exempt Information - Possible Exclusion of the Press and Public

4.

Minutes of the Meeting of the West Yorkshire and York Investment Committee held on 5 May pdf icon PDF 149 KB

5.

Capital Programme Update pdf icon PDF 475 KB

Additional documents:

Decision:

Resolved:

(i)              That the Investment Committee progress made in implementing the Combined Authority Capital Programmes be noted:

(ii)             That the exceptional circumstances principles relating to Transport Fund projects set out in paragraph 2.17 in the submitted report be approved

(iii)           That all Transport Fund projects that have requested additional funding will be considered on a case by case basis through the assurance process and reviewed against these exceptional principles.

 

6.

Transforming Cities Fund Programme Review pdf icon PDF 346 KB

Additional documents:

Decision:

Resolved:  

(i)              That the progress made in the delivery of the TCF programme, in particular the key messages presented on milestones, finances and risks be noted.

(ii)             That a further TCF Programme review be conducted over the next six months to report back to Committee in January 2022. This should consider opportunities to phase projects and accelerate delivery of schemes and associated spend.

(iii)           That partners develop plans to phase delivery of projects where possible to accelerate delivery to not only maximise spend but also deliver earlier benefits to users by March 2023

(iv)            That the guiding principles around allocation of the remaining risk/contingency and inflation detailed in section 2.20 be noted

(v)             That the Investment Committee recommended to the Combined Authority the changes to Indicative Funding Allocations set out in Table 1 of the submitted report.

(vi)           That the Investment Committee recommended to the Combined Authority approval to the £2.760m uplift in Programme Management budget to £7.690m to reflect the larger high scenario programme being delivered and anticipated longer timescales for delivery.

(vii)          That the Investment Committee recommended to the Combined Authority the following development funding to be released:

a)   Huddersfield Trinity St Access Improvements - £103,773

b)   Huddersfield Rail Station Access - £76,679

c)    A61 Bus, Cycle and Walking Improvements - £79,990

d)   Wakefield City Centre Bus, Cycle and Walking Improvements- £172,226

e)   A639 Bus, Cycle and Walking Improvements -£110,000

f)  York Tadcaster Road Corridor Improvement Scheme -£64,355

g)   Programme Development - £1.0m

 

7.

Capital Spending and Project Approvals pdf icon PDF 1004 KB

Additional documents:

Decision:

(i)              In respect of the Net Zero Region Accelerator the Investment Committee approved that:

(a)        The Net Zero Region Accelerator scheme proceeds through decision point 2 (Strategic Outline Case) and decision point 4 (Full Business Case) with Approval to Proceed to activity 5 (Delivery).

(b)        Approval to the Combined Authority’s contribution of £0.8 million (which will be funded from the Combined Authority’s gainshare to fund the economic recovery is given. The total scheme value is £0.8 million.

(c)        Future approvals be made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.

(ii)             In respect of the Health Innovation support the Investment Committee approved that:

(a)        The Health Innovation Support scheme proceeds through decision point 2 (Strategic Outline Case) and decision point 4 (Full Business Case) with Approval to Proceed to activity 5 (Delivery).

(b)        Approval to the Combined Authority’s contribution of £0.200 million (which will be funded from the Combined Authority’s gainshare to fund the economic recovery) is given.  The total scheme value is £0.200 million.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.

(iii)           In respect of the Entrepreneurship Package of Support the Investment Committee approved that:

(a)        The Entrepreneurship Package of Support project proceeds through decision point 2 (strategic outline case) and decision point 4 (full business case) with Approval to Proceed to activity 5 (delivery).

(b)        Approval to the Combined Authority’s contribution of £6 million, funded from the Combined Authority’s gainshare to fund the economic recovery, is given. The total scheme value is £6 million. 

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.

(iv)           In respect of the Housing Revenue Fund the Investment Committee recommended to the Combined Authority that:

(a)        The Housing Revenue Fund programme proceeds through decision point 2 (strategic outline case) and decision point 4 (full business case) with Approval to Proceed to activity 5 (delivery).

(b)        Approval to the remainder of the Combined Authority’s contribution of £2.95 million is given. The total scheme value if £3.2 million.

(c)        Allocation of the £2.95 million of funding for the individual work packages is delegated to the Managing Director.

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report.

(v)            In respect of the TCF: Skipton Railway Station Gateway – Active Travel Improvement Scheme the  Investment Committee approved that:

(a)        The Skipton Railway Station Gateway - Active Travel Improvement scheme proceeds through decision point 3 (Outline Business Case) and work commences on activity 4 (Full Business Case).

(b)        An indicative approval to the Combined Authority’s contribution of £7.631million (which will be funded from the Transforming Cities Fund) is given.  ...  view the full decision text for item 7.

7a

Entrepreneurship Package of Support

Decision:

(i)              In respect of the Entrepreneurship Package of Support the Investment Committee approved that:

(a)        The Entrepreneurship Package of Support project proceeds through decision point 2 (strategic outline case) and decision point 4 (full business case) with Approval to Proceed to activity 5 (delivery).

(b)        Approval to the Combined Authority’s contribution of £6 million, funded from the Combined Authority’s gainshare to fund the economic recovery, is given. The total scheme value is £6 million. 

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

7b

Transforming Cities Fund: Harrogate Railway Station Gateway - Active Travel Improvement Scheme

Decision:

(i)              That in respect of the TCF: Harrogate Railway Station Gateway – Active Travel Improvement Scheme the Investment Committee approved that:

(a)        The TCF Harrogate Railway Station Gateway - Active Travel Improvement scheme proceeds through decision point 3 (Outline Business Case) and work commences on activity 4 (Full Business Case).

(b)        An indicative approval to the Combined Authority’s contribution of £10.638 million (which will be funded from the Transforming Cities Fund) is given. The total scheme value is £10.938 million.

(c)        Development costs of £0.800 million are approved in order to progress the scheme to decision point 4 (Full Business Case) taking the total scheme approval to £1.445 million.

(d)        The Combined Authority enters into an addendum to the existing Funding Agreement with North Yorkshire County Council for expenditure of up to £1.445 million from the Transforming Cities Fund.

(e)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

7c

Transforming Cities Fund: Skipton Railway Station Gateway - Active Travel Improvement Scheme

Decision:

(i)              In respect of the TCF: Skipton Railway Station Gateway – Active Travel Improvement Scheme the Investment Committee approved that:

(a)        The Skipton Railway Station Gateway - Active Travel Improvement scheme proceeds through decision point 3 (Outline Business Case) and work commences on activity 4 (Full Business Case).

(b)        An indicative approval to the Combined Authority’s contribution of £7.631million (which will be funded from the Transforming Cities Fund) is given. The total scheme value is £7.831 million.

(c)        Development costs of £0.934 million are approved in order to progress the scheme to decision point 4 (Full Business Case) taking the total scheme approval to £1.360 million.

(d)        The Combined Authority enters into an addendum to the existing Funding Agreement with North Yorkshire County Council for expenditure of up to £1.360 million from the Transforming Cities Fund.

(e)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

7d

Net Zero Region Accelerator

Decision:

(i)              In respect of the Net Zero Region Accelerator the Investment Committee approved that:

(a)        The Net Zero Region Accelerator scheme proceeds through decision point 2 (Strategic Outline Case) and decision point 4 (Full Business Case) with Approval to Proceed to activity 5 (Delivery).

(b)        Approval to the Combined Authority’s contribution of £0.8 million (which will be funded from the Combined Authority’s gainshare to fund the economic recovery is given. The total scheme value is £0.8 million.

(c)        Future approvals be made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

7e

Health Innovation Support

Decision:

(i)              In respect of the Health Innovation support the Investment Committee approved that:

(a)        The Health Innovation Support scheme proceeds through decision point 2 (Strategic Outline Case) and decision point 4 (Full Business Case) with Approval to Proceed to activity 5 (Delivery).

(b)        Approval to the Combined Authority’s contribution of £0.200 million (which will be funded from the Combined Authority’s gainshare to fund the economic recovery) is given.  The total scheme value is £0.200 million.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.