Issue - meetings

Corridor Improvement Programme: Fink Hill, Leeds

Meeting: 04/03/2021 - ARCHIVED - West Yorkshire and York Investment Committee (Item 60)

Corridor Improvement Programme: Fink Hill, Leeds

Decision:

(i)              In respect of Fink Hill, Leeds the Investment Committee approved that:

(a)         The CIP Fink Hill Leeds scheme proceeds through decision point 4 and work commences on activity 5 (Full business case with finalised costs).

(b)        An indicative approval to the total scheme value of £5.428 million is given from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)         Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report. 

 

Minutes:

(i)              In respect of Fink Hill, Leeds the Investment Committee approved that:

(a)         The CIP Fink Hill Leeds scheme proceeds through decision point 4 and work commences on activity 5 (Full business case with finalised costs).

(b)        An indicative approval to the total scheme value of £5.428 million is given from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(c)         Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.