Rail Park and Ride Programme (Steeton & Silsden, Moorthorpe and Normanton schemes)

Meeting: 05/11/2020 - ARCHIVED - West Yorkshire and York Investment Committee (Item 27)

Rail Park and Ride Programme (Steeton & Silsden, Moorthorpe and Normanton schemes)

Decision:

(i)              In respect of the Rail Park and Ride Phase 1 (Steeton, Silsden, Moorthorpe, Normanton) the Investment Committee approved that:

(a)        An increase to the costs of the three schemes by £1.206 million to a total of £7.985 million. Individual scheme increases are Steeton and Silsden £0.752 million, Moorthorpe £0.127 million and Normanton £0.327 million.

(b)        To agree to extending the completion time scales for each scheme.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outline in this report.

 

Minutes:

(i)              In respect of the Rail Park and Ride Phase 1 (Steeton, Silsden, Moorthorpe, Normanton) the Investment Committee approved that:

(a)        An increase to the costs of the three schemes by £1.206 million to a total of £7.985 million. Individual scheme increases are Steeton and Silsden £0.752 million, Moorthorpe £0.127 million and Normanton £0.327 million.

(b)        To agree to extending the completion time scales for each scheme.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outline in this report.