LTP: Bus Station Safety & Security / Invest to Save
Decision:
(i) That in respect of the Safety, Accessibility and Efficiency Programme: Investing in Bus Stations, Shelters and Clean Growth Investment Committee approves that:
a) The Safety, Accessibility and Efficiency Programme: Investing in Bus Stations, Shelters and Clean Growth proceeds through decision point 2 and work commences on activity 4 (full business case)
b) An indicative approval to the Combined Authority’s contribution of £1.9 million from the Local Transport Plan – Integrated Transport Block fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5.
c) Development costs of £438,000 are approved to progress the scheme to decision point 5, taking the total approval to £438,000
d) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 4 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.
Minutes:
(i) That in respect of the Safety, Accessibility and Efficiency Programme: Investing in Bus Stations, Shelters and Clean Growth Investment Committee approves that:
a) The Safety, Accessibility and Efficiency Programme: Investing in Bus Stations, Shelters and Clean Growth proceeds through decision point 2 and work commences on activity 4 (full business case)
b) An indicative approval to the Combined Authority’s contribution of £1.9 million from the Local Transport Plan – Integrated Transport Block fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5.
c) Development costs of £438,000 are approved to progress the scheme to decision point 5, taking the total approval to £438,000
d) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 4 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.