Network Navigation
Additional documents:
Decision:
Resolved: That following a recommendation from the Investment Committee, the Combined Authority approves:
(i) That the Network Navigation (Leeds) scheme proceeds through decision point 3 (outline business case) and work commences on activity 5 (Full Business Case plus cost).
(ii) That an indicative approval to the total project value of £1.8 million is given from the LPTIP fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).
(iii) That development costs of £150,000 are approved in order to progress the scheme to decision point 5 (Full business case with finalised costs), taking the total project approval to £250,000.
(iv) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.
Minutes:
Resolved: That following a recommendation from the Investment Committee, the Combined Authority approves:
(i) That the Network Navigation (Leeds) scheme proceeds through decision point 3 (outline business case) and work commences on activity 5 (Full Business Case plus cost).
(ii) That an indicative approval to the total project value of £1.8 million is given from the LPTIP fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).
(iii) That development costs of £150,000 are approved in order to progress the scheme to decision point 5 (Full business case with finalised costs), taking the total project approval to £250,000.
(iv) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.