Resolved:  In respect of Leeds Bus Station Gateway -

That following a recommendation from the Investment Committee, the Combined Authority approves:

(a)       That the Leeds Public Transport Improvement Programme Leeds Bus Station Gateway project proceeds through decision point 3 (outline business case) and work commences on activity 5 (full business case with finalised costs)

(b)       That an indicative approval to the total project value of £4.984 million is given from the Leeds Public Transport Investment Programme fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs

(c)        That development costs of £350,000 are approved in order to progress the scheme to decision point 5.

(d)       That the Combined Authority enters into a variation to the Funding Agreement with Leeds City Council for release of expenditure of £350,000 from the LPTIP Fund for further project development.

(e)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.