(i) That in respect of the Conditioning House scheme the Investment Committee approves:
a) That the Conditioning House scheme proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs)
b) That an indicative approval to the total project value of £1.5 million is given from the Local Growth Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total scheme cost is £13.847 million
c) That future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.
Minutes:
(i) That in respect of the Conditioning House scheme the Investment Committee approves:
a) That the Conditioning House scheme proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs)
b) That an indicative approval to the total project value of £1.5 million is given from the Local Growth Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs). The total scheme cost is £13.847 million
c) That future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.