Getting Building Fund: Holbeck Phase 2 Victorian Terrace Retrofit

Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the scheme to progress through Activity 5 (Full Business Case with finalised costs).

Decision:

(i)              In respect of the Holbeck Phase 2 Victorian Terrace Retrofit the Investment Committee approves that:  

(a)        The GBF Holbeck Phase 2 scheme proceeds through decision point 5 (full business case with finalised costs) and work commences on activity 6 (delivery).  

(b)        Approval for the Combined Authority’s contribution of £2.604 million is given from the Getting Building Fund.

(c)        The Combined Authority enters into a funding agreement with Leeds City Council for expenditure of up to £2.604 million from the Getting Building Fund.

(d)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report subject to the scheme remaining within the tolerances outlined in this report

Report author: Elizabeth Courtney

Publication date: 03/12/2020

Date of decision: 02/12/2020

Decided at meeting: 02/12/2020 - ARCHIVED - West Yorkshire and York Investment Committee

Effective from: 11/12/2020