Decision details

Enterprise Zone: Parry Lane

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the scheme to progress through Activity 5 (Full Business Case with finalised costs).

Decision:

To approve that

·        Approval to an additional £1.276 million funding from the Local Growth Fund (LGF) for the Parry Lane Enterprise Zone scheme, taking the total approval to £1.886 million from the LGF is given. The total scheme value is £7.066 million.

·        The Combined Authority enters into a funding agreement with Bradford Council for expenditure up to £0.141 million from the LGF.

 

Reasons for the decision:

To ensure funding is in place to complete scheme development and to fund enabling works and the development of a biodiversity park at the Parry Lane Enterprise Zone site to the southeast of Bradford city centre.

Publication date: 27/11/2020

Date of decision: 20/11/2020

Effective from: 08/12/2020