Decision details

UTMC Element C

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the scheme to progress through Activity 5 (Full Business Case with finalised costs).

Decision:

To approve that:

 

·       The UTMC Element C scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

 

·       Approval to the total scheme value of £1.203 million is given from the West Yorkshire plus Transport Fund.

 

The Combined Authority enters into a Funding Agreement with Leeds City Council for expenditure of up to £1.203 million from the West Yorkshire-plus Transport Fund.

Reasons for the decision:

To enable a combined UTMC service for West Yorkshire to be delivered - combining the existing four UTC teams, to provide improved day-to-day management and coordination across the region’s road network through an integrated team at a single location.

 

Publication date: 01/09/2020

Date of decision: 28/08/2020

Effective from: 10/09/2020