Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to progress through
Activity 5 (Full Business Case with finalised costs).
To approve that:
· The UTMC Element C scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).
· Approval to the total scheme value of £1.203 million is given from the West Yorkshire plus Transport Fund.
The Combined Authority enters into a Funding Agreement with Leeds City Council for expenditure of up to £1.203 million from the West Yorkshire-plus Transport Fund.
To enable a combined UTMC service for West Yorkshire to be delivered - combining the existing four UTC teams, to provide improved day-to-day management and coordination across the region’s road network through an integrated team at a single location.
Publication date: 01/09/2020
Date of decision: 28/08/2020
Effective from: 10/09/2020