Decision Maker: Director, Finance & Commercial Services
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to progress through
Activity 5 (Full Business Case with finalised costs) and work
commence on Activity 6 (Delivery).
To approve that:
· The Network Navigation (Leeds) scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).
Approval to the total project value of £1.8 million is given from the Leeds Public Transport Investment Programme fund.
To enable work to commence on the scheme which will deliver a package of user friendly, highly visible materials to help customers identify and navigate the bus network in Leeds, improving transport accessibility and user experience by providing an accessible network map, linked to new colour coded bus stop flags and shelters.
Publication date: 05/08/2020
Date of decision: 31/07/2020
Effective from: 14/08/2020