Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to proceed through
Activity 3 (Outline Business Case) and work commence on Activity 4
(Full Business Case).
Resolved: That following a recommendation from the Investment Committee, the Combined Authority approves:
(a) That the East Leeds Demand Responsive Transport scheme proceeds through decision point 3 and work commences on activity 5 (full business case with finalised costs).
(b) That an indicative approval to the total project value of £2.234 million, is given with the Combined Authority’s funding contribution of £1.466 million (Leeds Public Transport Investment Programme (LPTIP) – £763,000, Local Transport Plan – Integrated Transport Block Programme - £703,000) with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(c) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.
Report author: Kate Gifford
Publication date: 25/06/2020
Date of decision: 25/06/2020
Decided at meeting: 25/06/2020 - West Yorkshire Combined Authority
Effective from: 03/07/2020