Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enable work to commence on four schemes
within the Transport Hubs and Connecting Communities workstream of
the Connecting Leeds Programme.
The four individual schemes are: Bramley Bus Interchange; Compton
Road Bus Stop Improvements, Harehills; Lincoln Green Walking and
Cycling Links; and Pudsey Walking and Cycling Links.
These will create new or upgrade existing facilities to improve the
waiting environment and travel information offer as well as
enhancing connections within and between other public transport
hubs and communities by improving walking and cycling links.
To approve that
• The Transport Hubs and Public Transport Access Schemes phase
1 project proceeds through decision point 5 of the Combined
Authority’s assurance process and work commences on activity
6 (Delivery).
• Approval is given to the total project value of £4.26
million from the Leeds Public Transport Investment Programme
fund.
• The Combined Authority enters into an addendum to the
existing Funding Agreement with Leeds City Council for expenditure
up to £4.26 million from the Leeds Public Transport
Investment Programme fund.
Publication date: 20/04/2020
Date of decision: 21/02/2020