Decision details

A65 Signals Scheme

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To enable work to commence on the upgrading of traffic signals at junctions along the inner section of the A65 to the northwest of Leeds city centre between the junction with the B6157 (including Savins Mill and Wyther Lane) and the Inner Ring Road (A58) with the aim to improve journey times for bus services along the corridor as well as increasing bus patronage.

Decision:

To approve that
• The A65 Signals scheme proceeds through decision point 5 of the Combined Authority’s assurance process and work commences on activity 6 (Delivery).
• Approval of £956,000 is given from the LPTIP fund towards the total scheme cost of £1.209 million with LCC providing match funding of £253,000
• The Combined Authority is to enter into an addendum to the existing Funding Agreement with Leeds City Council for expenditure of up to £956,000 from the LPTIP fund.

Publication date: 17/02/2020

Date of decision: 14/02/2020