Decision details

Connecting Innovation (Economic Scheme)

Decision Maker: West Yorkshire Combined Authority

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the Connecting Innovation Scheme to proceed through Decision Point 2 (Strategic Outline Case) and work commence on Activity 5 (Full Business Case with Finalised Costs).

Decisions:

Resolved:  In respect of ERDF – Connecting Innovation -

That following a recommendation from the Investment Committee, the Combined Authority approves:

(a)       That the ERDF Connecting Innovation project proceeds through decision point 2 and work commences on Activity 5 (full business case plus).

(b)       That an indicative approval of £2,779,846, comprised of £750,961 from the Access to Capital Grants element of the Local Growth Fund and £2,028,885 from the European Regional Development Fund. The total project costs are £4,057,771 million, with Small Medium Enterprise match funding of £1,277,925 million.

(c)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team.  This will be subject to the scheme remaining within the tolerances outlined in the report.

Report author: Angie Shearon

Publication date: 13/01/2020

Date of decision: 09/01/2020

Decided at meeting: 09/01/2020 - West Yorkshire Combined Authority

Effective from: 21/01/2020