Decision details

Wakefield South East Gateway - Rutland Mills

Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the Wakefield South East Gateway - Rutland Mills scheme to proceed through Decision Point 4 (Full Business Case) and work commence on Activity 5 (Full Business Case with Finalised Costs).

Decisions:

Resolved: That in respect of the Wakefield City Centre, South East Gateway – Rutland Mill the Investment Committee using the delegated authority from the Combined Authority Board approved:

(a)       That the Wakefield City Centre, South East Gateway – Rutland Mill proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).

(b)       That an indicative approval to the Combined Authority’s capped contribution of £2.89 million to the Rutland Mill scheme to be funded from the Local Growth Fund programme is given towards a total scheme cost of £20.57 million with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(c)       That decision point 5 (full business case with finalised costs) is conditional upon the Wakefield Council providing a finalised development contract which demonstrates that if 100% of the floor space isn’t developed by December 2022, Wakefield can step in to buy back at 70% market value.

(d)       That future approvals are made in accordance with the assurance pathway and approval route outlined in this report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

Report author: Lisa Childs

Publication date: 05/12/2019

Date of decision: 04/12/2019

Decided at meeting: 04/12/2019 - ARCHIVED - West Yorkshire and York Investment Committee

Effective from: 13/12/2019