Decision details

A629 Phase 1a, Calderdale (change request)

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To enable completion of the A629 phase 1a (Salterhebble to Shaw Hill) scheme in Calderdale, which is currently in construction, leading to improved journeys and air quality and improved facilities for pedestrians, cyclists and public transport. Also to ensure the correct funding allocations are in place for the overall A629 programme monitoring budget.

Decision:

To approve the change request to the A629 phase 1a scheme authorizing additional £343,344 delivery costs, and the re-allocation of £39,812 from the post construction evaluation budget into the A629 (programme) monitoring budget. This takes the total outturn cost for the scheme to £8,639,999.

To approve that the Combined Authority enters into an addendum to the existing funding agreement with Calderdale Metropolitan Borough Council for additional expenditure of up to £343,344 from the West Yorkshire Plus Transport Fund.

Publication date: 16/10/2018