Approval for the scheme to progress through Activity 5 (Full Business Case plus finalised costs)

Decision:

To approve that

 

·        The Corridor Improvement Programme Calderdale A646-A6033 Corridor scheme proceeds through decision point 5 and work commences on activity 6 (Delivery).

 

·        Approval to the total Combined Authority contribution of £3.988 million, to be funded through the West Yorkshire plus Transport Fund, is given. The total scheme value is £4.313 million, with a £0.325 million match contribution from Calderdale Council.

 

·        The Combined Authority enters into an addendum to the existing funding agreement with Calderdale Council for expenditure of up to £3.988 million from the West Yorkshire plus Transport Fund.

 

Reasons for the decision:

To enable delivery to commence on a package of work to improve highway traffic flow for the benefit of all road users, particularly improved bus, walking and cycling facilities, along the A646-A6033 corridor, Calderdale, between Todmorden and Skircoat Moor via Hebden Bridge, Mytholmroyd and Luddenden Foot.

Publication date: 02/08/2021

Date of decision: 30/07/2021

Effective from: 10/08/2021