Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to progress through
Activity 5 (Full Business Case with finalised costs) and work
commence on Activity 6 (Delivery).
Resolved: That in respect to Transforming Cities Fund
Halifax Bus Station, the Combined Authority approves:
(i) That the
Transforming Cities Fund Halifax Bus Station scheme proceeds
through decision point 5 and work commences on activity 6
(Delivery).
(ii) That approval to total
scheme costs of £17.700 million is given, of which the
Combined Authority to contribute £17.295 million from the
Transforming Cities Fund and £0.405 million from the West
Yorkshire plus Transport Fund.
(iii) That the Combined
Authority enters into a Memorandum of Understanding Agreement with
Calderdale Council for expenditure up to £50,000 from the
Transforming Cities Fund.
(iv) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report. This will be subject to the scheme remaining within the tolerances outlined in the report.
Report author: Mark Auger
Publication date: 29/07/2021
Date of decision: 29/07/2021
Decided at meeting: 29/07/2021 - West Yorkshire Combined Authority