Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enable delivery to continue on LRF schemes
in Wakefield and Craven contributing to the completion of 74
housing units across the LRF programme.
To approve that:
i. The change request to the Land Release Fund (LRF) programme is
approved. This confirms that the overall LRF programme cost is
£475,875.
ii. The delivery timeframe for Craven’s Airedale Avenue and
Wakefield’s Langthwaite Lane projects within the LRF
programme is extended to March 2022.
iii. The Combined Authority enters into a funding agreement with
Wakefield Council for expenditure of up to £19,375 from the
Land Release Fund.
iv. The Combined Authority extends the funding agreement with
Craven District Council for the Airedale Avenue site until the end
of March 2022.
Publication date: 21/07/2021
Date of decision: 16/07/2021