Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To enable works to reinstate the A6025 Park Road following a landslip in February 2020 which led to its full closure throughout last year and stopped east-west traffic movements between Elland and Brighouse. This will unlock 0.5 km of highway and will re-connect Elland and Brighouse.
(i) In respect of the GBF: Brighouse Reconstruction the Investment Committee approved that:
(a) The Getting Building Funding (GBF); Brighouse A6025 Reconstruction scheme proceeds through decision point 4 (full business case) and work commences on activity 5 (full business case with finalised costs).
(b) Indicative approval to the Combined Authority’s contribution of £1.8 million is given from the Getting Building Fund (GBF) with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(c) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.
Report author: Rob Tranmer
Publication date: 05/03/2021
Date of decision: 04/03/2021
Decided at meeting: 04/03/2021 - ARCHIVED - West Yorkshire and York Investment Committee
Effective from: 13/03/2021