Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To ensure funding is in place to enable
property acquisition to take place on the Castleford Growth
Corridor scheme which will deliver highway improvements as well as
provision of new and enhanced cycle way and pedestrian footpaths
along the corridor.
To approve that
•The change request to the Castleford Growth Corridor scheme
for an additional £0.4 million development costs from the
West Yorkshire plus Transport Fund is approved, taking the total
approval from the West Yorkshire plus Transport Fund to
£2.239 million.
•The Combined Authority enters into a funding agreement with
Wakefield Council for expenditure up to £2.239 million from
the West Yorkshire plus Transport Fund.
Publication date: 31/03/2021
Date of decision: 12/02/2021