Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
(i) The Investment Committee approves:
(a) The reallocation of schemes to other funding programmes as outlined in Appendix 1 (table 2)
(b) The reprofiled decision point 2 development costs, as set out in Appendix 1 (table 3)
(c) Additional development costs of £1.273 million for A58 Beckett Street, bringing the total development costs to £1.779 million from the LPTIP Fund
(d) That authority is delegated to the Combined Authority’s Managing Director to approve, via a Change Request, additional development costs from the LPTIP Fund for the A58 Beckett Street scheme, should the costs be affordable within the LPTIP programme.
(e) Additional development costs of £0.716 million for Alwoodley Gates Park and Ride bringing the total development costs to £0.916 million from the LPTIP Fund
(g) That the Combined Authority issues addendums to the existing Funding Agreements with Leeds City Council for expenditure from the LPTIP Fund.
Publication date: 08/01/2021
Date of decision: 07/01/2021
Decided at meeting: 07/01/2021 - ARCHIVED - West Yorkshire and York Investment Committee
Effective from: 16/01/2021