Decision details

A6110/Leeds City Centre Package

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To ensure funding is in place to enable development work to continue on the A6110 Ring Road (Leeds) improvement scheme and the City Square element of the Leeds City Centre Package, both funded through the West Yorkshire plus Transport Fund.

Decision:

To approve that
•The development costs of £0.310 million for the A6110 Outer Ring Road (Leeds) scheme, to progress the scheme to decision point 3 (Outline Business Case), taking the total scheme development costs from £0.286 million to £0.596 million.
•The transfer of £1.5 million from Armley Gyratory West Yorkshire plus Transport Fund development costs to City Square+, taking the total from £5.080 million to £3.580 million.
•An increase to the City Square+ development costs (from Armley Gyratory) taking the total development costs from £3.774 million to £5.274 million to progress to decision point 5 (Full Business Case plus finalised costs).
•The Combined Authority enters into addendums to the relevant existing funding agreements for the above schemes with Leeds City Council.

Alternative options considered:

Option 1 -
Option 2 -
Option 3 -

Publication date: 11/11/2020

Date of decision: 06/11/2020