Decision details

Rail Park and Ride Programme (Steeton & Silsden, Moorthorpe and Normanton schemes)

Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the Activity 5 (Full Business Case with Finalised costs) Change Request. This change request is seeking approval for an increase in the scheme approvals, contract values and timescales for each of the 3 schemes mentioned above.

Decision:

(i)              In respect of the Rail Park and Ride Phase 1 (Steeton, Silsden, Moorthorpe, Normanton) the Investment Committee approved that:

(a)        An increase to the costs of the three schemes by £1.206 million to a total of £7.985 million. Individual scheme increases are Steeton and Silsden £0.752 million, Moorthorpe £0.127 million and Normanton £0.327 million.

(b)        To agree to extending the completion time scales for each scheme.

(c)        Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outline in this report.

 

Report author: John Parkin

Publication date: 09/11/2020

Date of decision: 05/11/2020

Decided at meeting: 05/11/2020 - ARCHIVED - West Yorkshire and York Investment Committee

Effective from: 17/11/2020