Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to proceed through
Decision Point 2 (Strategic Outline Case) and work commence on
Activity 3 (Outline Business Case).
Resolved: That following a recommendation from the Investment Committee, the Combined Authority approves:
(a) That the A64 Bus Priority & Park & Ride package proceeds through decision point 2 (strategic outline case) and work commences on activity 3 (outline business case).
(b) That an indicative approval of £7 million is given from the Transforming Cities Fund with full approval to spend being granted once the scheme package has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(c) That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Portfolio Appraisal Team. This will be subject to the package remaining within the tolerances outlined in the report.
Report author: Fiona Limb
Publication date: 27/07/2020
Date of decision: 27/07/2020
Decided at meeting: 27/07/2020 - West Yorkshire Combined Authority
Effective from: 04/08/2020