Decision details

Corporate Technology Programme – Final packages

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To approve that the next (and final) phase of the following Corporate Technology Programme (CTP) work packages:
oB06 Data Platform
oB07 Meeting Room Technology
oC01 Cyber Security
oC02 ICT Disaster Recovery
oE02 Digitising Services
proceeds through decision point 5 of the Combined Authority’s assurance process as a programme of work and work commences on activity 6 (Delivery).
To approve the total value of these packages of £577,959 from the allocated programme budget.

Decision:

To enable work to commence on the delivery of the final packages of work as included in the Combined Authority’s Corporate Technology Strategy (CTS) as approved in March 2018.

Alternative options considered:

Option 1 -
Option 2 -
Option 3 -

Publication date: 31/03/2021

Date of decision: 17/07/2020