Decision Maker: ARCHIVED - West Yorkshire and York Investment Committee
Decision status: Recommendations approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the A629 (Phase1b) – Elland
Wood Bottom to Salterhebble Hill Activity 4 (Full Business Case)
and work commence on Activity 5 (Full Business Case with Finalised
Costs).
(i) That in respect of the A629 Phase 1b the Investment Committee recommended that:
(a) The A629 phase 1b project proceeds through decision point 4 and work commences on activity 5 (Full business case with finalised costs).
(b) An indicative approval to the total project value of £27.83 million is given from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).
(c) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in this report.
Report author: Caroline Coy
Publication date: 09/07/2020
Date of decision: 08/07/2020
Decided at meeting: 08/07/2020 - ARCHIVED - West Yorkshire and York Investment Committee
Effective from: 17/07/2020