Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enable Leeds City College to complete
delivery of the project to develop advanced training facilities for
the delivery of its healthcare and life science technical skills
& training at its newly constructed Quarry Hill campus, along
with the refurbishment of poor quality accommodation at the Park
Lane campus.
To approve that:
• The change request for the Leeds City College (Quarry Hill)
project for a change in scope for the Park Lane campus
refurbishment is approved.
• The change request for the exceeding of the Combined
Authority’s time tolerance by taking the theatre works out of
the main Quarry Hill build contract is approved
Publication date: 23/06/2020
Date of decision: 22/06/2020