Purpose:

To enable delivery to commence on the Harrogate Road New Line junction improvement scheme which will improve the existing junction at Greengates, Bradford, including widening of the existing highway on all four arms of the junction, signal upgrades, junction improvements and improvements for pedestrians and cyclists.

Decision:

To approve that:
• The Harrogate Road-New Line scheme proceeds through decision point 5 of the Combined Authority’s assurance process and work commences on activity 6 (Delivery)
• Approval is given to the Combined Authority’s contribution of £7.665 million (which will be funded through West Yorkshire Plus Transport Fund (WY+TF)). Match funding is supplied by City of Bradford Metropolitan Council (£2.736 million) and private sector contributions (£1.926 million). The total project value is £12.327 million.
• The Combined Authority enters into a Funding Agreement with City of Bradford Metropolitan District Council for expenditure of up to £7.665 million from the West Yorkshire Plus Transport Fund.

Publication date: 12/02/2020

Date of decision: 07/02/2020