Decision details

Capital Spending and Project Approvals

Decision Maker: West Yorkshire Combined Authority

Decision status: Information Only

Is Key decision?: No

Is subject to call in?: Yes

Decision:

Resolved:

 

(a)       In respect of Leeds Transport Model Update 2020 –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

 

(i)         That the Leeds Transport Model Update 2020 project proceeds through Decision Point 2 and work commences on Activity 5 (full business case with finalised costs).

(ii)        That an indicative approval of £600,000 is given from the West Yorkshire plus Transport Fund towards a total scheme cost of £1.2 million with full approval to spend being granted once the scheme has progressed through the assurance process to Decision Point 5.

(iii)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at Decision Point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(b)       In respect of York City Centre Access Improvements –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the York City Centre Access Improvements scheme proceeds through decision point 2 (strategic outline case) and work commences on activity 3 (outline business case).

(ii)        That an indicative approval to the total project value of £8.1 million is given from the West Yorkshire-plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5.

(iii)       That development costs of £355,000 be approved in order to progress the scheme to activity 3 (outline business case).

(iv)       That the Combined Authority enters into a Funding Agreement with City of York Council for expenditure of up to £355,000 from the West Yorkshire-plus Transport Fund.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 4 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances set out in the report.

(c)        In respect of Leeds City Region Future Mobility Zone –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

 

(i)         That the Future Mobility Zone (FMZ) programme proceeds through Decision Point 2 and work commences on the development of business cases for individual packages

(ii)        That an indicative approval to £30.793 million, which will be funded from the Local Transport Plan (£2.75 million), the Leeds Public Transport Investment Programme (£0.763 million) and the Department for Transport FMZ fund (£27.28 million) is given with full approval to spend being granted as individual scheme or packages have progressed through the Assurance Process to Decision Point 5. The total programme cost is £32.01 million, including £1.22 million from District Partners.

(iii)       That an approval for development funding of £2.01 million be made to enable initial work on outline business cases for individual packages, subject to DfT funding being announced.

(iv)       That future programme approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at Decision Point 6 and 7 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(d)       In respect of Hebden Bridge Flood Alleviation –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)        That the Hebden Bridge Flood Alleviation Scheme proceeds through decision point 3 and work commences on activity 4 (full business case)

(ii)       That development costs of £1.9 million are approved in order to progress the scheme to activity 4 (full business case) from the Local Growth Fund. The total project value is £27.283 million.

(iii)      That the Combined Authority enters into a Funding Agreement with the Environment Agency for development expenditure of up to £1.9 million from the Local Growth fund.

(iv)      That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(e)       In respect of Corn Exchange Gateway –

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Corn Exchange Gateway project proceeds through decision point 3 and work commences on activity 4 (FBC).

(ii)        That an indicative approval to the Combined Authority’s contribution of £24.7 million is given, with £18.6 million to be funded through the Leeds Public Transport Investment Programme and £6.1 million from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (FBC with finalised costs). The total project value is £25.6 million.

(iii)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 4 and 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(f)        In respect of Enterprise Zone: Parry Lane –

 

That following a recommendation from the Investment, the Combined Authority approves:

(i)         That the EZ Parry Lane scheme proceeds through decision point 3 and work commences on activity 4 (full business case).

(ii)        That the total cost of the scheme is £18.88 million. An indicative approval to the Combined Authority’s contribution of £8.081 million through the Local Growth Fund is given, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That development costs of £540,000 are approved in order to progress the scheme to decision point 4 (full business case).

(iv)       That approval is given to enter into a Funding Agreement with the City of Bradford District & Metropolitan Council in order to assist in the development of the full business case for up to £540,000.

(v)        That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 4 and 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(g)       In respect of Leeds Inland Port -

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Leeds Inland Port project proceeds through decision point 3 and work commences on activity 4 (Full business case).

(ii)        That an indicative approval to the Combined Authority’s contribution of £3.17 million is given, to be funded from the West Yorkshire plus Transport Fund, with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (FBC with finalised costs). The total project value is £3.37 million.

(iii)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report, including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(h)       In respect of Leeds Bradford Airport Parkway –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Leeds Bradford Airport Parkway project proceeds through decision point 3 and work commences on activity 4 (full business case).

(ii)        That indicative approval to the total project value of £5 million has been given from the LPTIP fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).

(iii)       That the development costs of £4.5 million are approved in order to progress the scheme to decision point 4 (Full business case), taking the total project approval to £5 million.

(iv)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report, including at decision point 4 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team (subject to the scheme remaining within the tolerances outlined in the report), with decision point 5 approval through a delegation to the Investment Committee following a recommendation by the Combined Authority’s Programme Appraisal Team.

(i)         In respect of Network Navigation –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Network Navigation (Leeds) scheme proceeds through decision point 3 (outline business case) and work commences on activity 5 (Full Business Case plus cost).

(ii)        That an indicative approval to the total project value of £1.8 million is given from the LPTIP fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (Full business case with finalised costs).

(iii)       That development costs of £150,000 are approved in order to progress the scheme to decision point 5 (Full business case with finalised costs), taking the total project approval to £250,000.

(iv)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Managing Director following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(j)         In respect of Moorthorpe Rail Car Park –

 

That following a recommendation from the Investment Committee, the Combined Authority approves:

(i)         That the Moorthorpe Rail Car Park project proceeds through decision point 5 and work commences on activity 6 (Delivery).

(ii)        That approval to the total project value of £778,551 million is given from the West Yorkshire plus Transport Fund. 

(iii)       That approval for the Combined Authority to enter into a Section 56 Funding Agreement with Arriva Rail North for expenditure of up to £635,000 million from the West Yorkshire plus Transport Fund.

(iv)       That approval for the Combined Authority to enter into a Basic Asset Protection Agreement with Network Rail for £32,000.

(v)       That future approvals are made in accordance with the assurance pathway and approval route outlined in the submitted report following a recommendation by the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.

(k)        In respect of Clifton Business Park –

 

That following a recommendation from the Investment Committee, the Combined Authority approves that a funding agreement be entered into with Calderdale Council for expenditure of up to £3.156 million from the Local Growth Fund for the Clifton Business Park (Enterprise Zone) as approved by the Combined Authority on 10 October 2019.

 

Publication date: 06/02/2020

Date of decision: 06/02/2020

Decided at meeting: 06/02/2020 - West Yorkshire Combined Authority

Effective from: 14/02/2020

Accompanying Documents: