Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enable delivery to commence on the new park
and ride site adjacent to the M621 Junction 7 in Stourton, Leeds,
which when completed would accommodate a maximum of 1,200 car
parking spaces as well as providing a very high quality,
all-electric bus service to Leeds city centre.
To approve that:
• The Stourton Park & Ride project proceeds through
decision point 5 and work commences on activity 6 (delivery).
• Approval to the Combined Authority’s contribution of
£35.67 million funded from the Leeds Public Transport
Investment Programme fund, is given. The total project value is
£38.5 million.
• The Combined Authority adds a project schedule to the
existing Funding Agreement with Leeds City Council for expenditure
of up to £35.67 million from the Leeds Public Transport
Investment Programme fund.
Publication date: 03/02/2020
Date of decision: 31/01/2020