Decision details

Stourton Park & Ride

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To enable delivery to commence on the new park and ride site adjacent to the M621 Junction 7 in Stourton, Leeds, which when completed would accommodate a maximum of 1,200 car parking spaces as well as providing a very high quality, all-electric bus service to Leeds city centre.

Decision:

To approve that:
• The Stourton Park & Ride project proceeds through decision point 5 and work commences on activity 6 (delivery).
• Approval to the Combined Authority’s contribution of £35.67 million funded from the Leeds Public Transport Investment Programme fund, is given. The total project value is £38.5 million.
• The Combined Authority adds a project schedule to the existing Funding Agreement with Leeds City Council for expenditure of up to £35.67 million from the Leeds Public Transport Investment Programme fund.

Publication date: 03/02/2020

Date of decision: 31/01/2020