Decision Maker: West Yorkshire Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the Leeds City Centre Package -
Infirmary Street Gateway scheme to proceed through Decision Point 4
(Full Business Case) and work commence on Activity 5 (Full Business
Case with Finalised Costs).
Resolved: In respect of LCCP Infirmary Street -
That following a recommendation from the Investment Committee, the Combined Authority approves:
(a) That the Infirmary Street Gateway scheme proceeds through decision point 4 and work commences on activity 5 (full business case with finalised costs).
(b) That an indicative approval to the total project value of £8.90 million is given from the West Yorkshire plus Transport Fund with full approval to spend being granted once the scheme has progressed through the assurance process to decision point 5 (full business case with finalised costs).
(c) That future approvals are made in accordance with the Assurance pathway and Approval route outlined in the submitted report including at decision point 5 through a delegation to the Combined Authority’s Programme Appraisal Team. This will be subject to the scheme remaining within the tolerances outlined in the report.
Report author: Lisa Childs
Publication date: 13/01/2020
Date of decision: 09/01/2020
Decided at meeting: 09/01/2020 - West Yorkshire Combined Authority
Effective from: 21/01/2020