Decision details

Active Travel Fund Tranche 4 - Silsden to Kildwick Towpath, Bradford

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval for the scheme to proceed through decision points 2 to 4 (business justification) to upgrade a 1.2km section of the Leeds & Liverpool Canal towpath.

Decision:

The Chief Executive approves that (subject to conditions):

 

i.                 The Silsden to Kildwick Canal Towpath scheme proceeds through decision point 2 to 4 (business justification) and work commences on activity 5 (delivery).

 

ii.                 Approves the Combined Authority’s contribution of £1,053,429. The total scheme value is £2,027,885.

 

iii.              Approves that the Combined Authority enters into an addendum to the existing Funding Agreement with City of Bradford Metropolitan District Council for expenditure of up to £1,053,429

 

iv.              Approves that future approvals are made in accordance with the assurance pathway and approval route and tolerances outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.

 

Reasons for the decision:

To approve the Business Justification Case to enable work to commence, subject to conditions, on the scheme to upgrade the Leeds-Liverpool Canal towpath between Silsden and Kildwick

 

Publication date: 02/01/2025

Date of decision: 18/12/2024

Effective from: 10/01/2025