Decision details

Dewsbury - Cleckheaton Sustainable Travel Corridor

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To enable the Dewsbury – Cleckheaton Sustainable Transport Corridor scheme to proceed through decisionpoint 4 (full businesscase) of the Combined Authority’sassurance process and for work to commence on activity 5 (Delivery) subjectto conditions set by the Combined Authority’s Portfolio Investment Panel.

Decision:

Approval to the Combined Authority’s contribution of £15,799,977 is given subject to an Approval to Proceed. The total scheme value is £15,799,977.

 

Approval of additional development costs of £854,355, taking the total approval to £2,782,005 to progress the scheme to Approval to Proceed, is given.

 

The Combined Authority enters into an addendum to the existing Funding Agreement with Kirklees Council for expenditure of up to £2,782,005.

 

Publication date: 22/03/2024

Date of decision: 19/03/2024

Effective from: 30/03/2024