Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval for the scheme to progress through
Activity 4 (Full Business Case)
(i) Phase 1 of the Leeds City Centre Package Armley Gyratory scheme proceeds through decision point 4 and work commences on activity 5 (Delivery).
(ii) Approval of £27,930,000 for Phase 1 of the Leeds City Centre Package Armley Gyratory scheme is given from the West Yorkshire plus Transport Fund, bringing the total approved to £31,510,000.
(iii) Phase 2 of the Leeds City Centre Package Armley Gyratory scheme continues to develop its Final Business Case.
(iv) Indicative Approval of £10,460,000 for Phase 2 of the Leeds City Centre Package Armley Gyratory scheme is given from the West Yorkshire plus Transport Fund.
(v) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.
Conditions
The following conditions have been set by PAT to gain Approval to Proceed to Delivery for Phase 1:
(i) Complete detailed design to inform a Target Cost (price) affordable to the scheme.
(ii) Conclude land acquisition and secure required licenses.
(iii) Evidence pre-scheme (Autumn 2021) Monitoring & Evaluation data capture
Publication date: 07/01/2022
Date of decision: 07/01/2022
Effective from: 15/01/2022