Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
(i) The York Castle Gateway scheme proceeds through decision point 3 and work commences on activity 4 (Full business case)
(ii) An indicative approval to the total value of £4,600,000 is given from the West Yorkshire plus Transport Fund with full approval to spend once the package has progressed through the assurance process to decision point 5.
(iii) Future approvals are made in accordance with the assurance pathway and approval route outlined in this report. This will be subject to the scheme remaining within the tolerances outlined in this report.
Publication date: 07/01/2022
Date of decision: 06/01/2022
Effective from: 15/01/2022