Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Approval of Activity 3 (Outline Business Case)
Change Request.
To approve that:
· The change request to the York Northern Outer Ring Road scheme for additional development costs of £3.131 million from the West Yorkshire plus Transport Fund, to enable the scheme to continue to progress to decision point 4 (Full Business Case) is approved, bringing the total development costs to £5.581 million.
To enable development work to continue on the scheme which is delivering improvements to 7 existing roundabouts on the York Northern Outer Ring Road between the Wetherby Road and Monks Cross junctions.
Publication date: 24/05/2021
Date of decision: 21/05/2021
Effective from: 01/06/2021
Accompanying Documents: