Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enable development work to continue on the
scheme aiming to deliver a new ‘parkway’ station
between Horsforth Station and the southern entrance to Bramhope
tunnel on the Harrogate Line with the station serving one of the
region’s key Employment Growth spatial priority areas and
Leeds Bradford Airport as well as serving as a Park and Ride for
commuters into Leeds, York, Harrogate and beyond.
To approve that:
• The change request to the Leeds Bradford Airport Parkway
Station scheme for additional development costs of £0.650
million from the West Yorkshire plus Transport Fund, to enable the
scheme to continue to progress to decision point 4 (Full Business
Case) is approved, bringing the total development costs to
£5.650 million.
Publication date: 11/05/2021
Date of decision: 07/05/2021