Decision details

Leeds Bradford Airport Parkway Station

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To enable development work to continue on the scheme aiming to deliver a new ‘parkway’ station between Horsforth Station and the southern entrance to Bramhope tunnel on the Harrogate Line with the station serving one of the region’s key Employment Growth spatial priority areas and Leeds Bradford Airport as well as serving as a Park and Ride for commuters into Leeds, York, Harrogate and beyond.

Decision:

To approve that:
• The change request to the Leeds Bradford Airport Parkway Station scheme for additional development costs of £0.650 million from the West Yorkshire plus Transport Fund, to enable the scheme to continue to progress to decision point 4 (Full Business Case) is approved, bringing the total development costs to £5.650 million.


Publication date: 11/05/2021

Date of decision: 07/05/2021