Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enable development work to continue on the
scheme which will deliver improved town centre walking routes, and
improved walking and cycling facilities and crossings of the
Dewsbury Ring Road, to give greater pedestrian links to the north
east of Dewsbury town centre and better access to Dewsbury
College.
To approve that:
The change request for the Transforming Cities Fund (TCF) Dewsbury
Town Centre Walking and Cycling Improvements scheme for an
additional £0.209 million from the TCF to progress the scheme
to outline business case is approved. The total approval from the
TCF is now £0.575 million.
The Combined Authority enters into an addendum to the existing
Funding Agreement with Kirklees Council for the Dewsbury Town
Centre Walking and Cycling Improvements scheme, for expenditure up
to £0.575 million, from the Transforming Cities
Fund.
Publication date: 11/05/2021
Date of decision: 07/05/2021